Oklahoma

Oklahoma hosts 9 documented datacenter projects representing $21.4B in announced investment and 310 MW of power capacity.

State Overview 9 documented projects
$21.4B
Announced Investment
310 MW
Planned Power Capacity
#13
Investment Rank
#39
Power Rank

Project Status Breakdown

Planned
3
33% of projects
Under Construction
3
33% of projects
Operational
2
22% of projects
Expansion
1
11% of projects

All Projects in Oklahoma

9 projects
Project Location Investment Power Status
Google Mayes County (Pryor) Data Center Expansion
Google LLC
Pryor $9.0B N/A Expansion
Project Clydesdale (Tulsa County/Owasso)
Beale Infrastructure, Unknown hyperscaler
Owasso $4.5B N/A Planned
CoreWeave/Core Scientific Muskogee Data Center
CoreWeave, Core Scientific
Muskogee $4.0B 100 MW Under Construction
Google Stillwater Data Center Campus
Google LLC
Stillwater $3.0B N/A Under Construction
Project Anthem (Tulsa East)
Unknown (believed to be Meta Platforms)
Tulsa $800M N/A Planned
Polaris Technologies Bitcoin Mining Data Center
Polaris Technologies Inc.
Muskogee $100M 200 MW Under Construction
TierPoint Oklahoma City Data Center Expansion
TierPoint LLC
Oklahoma City $30M N/A Operational
Cerebras Systems Oklahoma City AI Data Center
Cerebras Systems, Scale Datacenters
Oklahoma City N/A 10 MW Operational
DAMAC/EDGNEX Oklahoma Data Centers
DAMAC Group, EDGNEX Data Centers
Unknown N/A N/A Planned

Oklahoma Data Center Infrastructure

Oklahoma hosts 9 documented datacenter projects representing $21.4B in disclosed investment and 310 MW of power capacity.

Key Statistics

MetricValue
Total Projects9
Total Investment$21.4B
Total Power Capacity310 MW
Investment Rank#13
Power Rank#39
Grid OperatorSPP

Project Status Breakdown

  • Under Construction: 3 projects
  • Planned: 3 projects
  • Operational: 2 projects
  • Expansion: 1 projects

Top Projects

Google Mayes County (Pryor) Data Center Expansion

  • Location: Pryor
  • Investment: $9.0B
  • Power: N/A
  • Status: Expansion
  • Sponsors: Google LLC

Project Clydesdale (Tulsa County/Owasso)

  • Location: Owasso
  • Investment: $4.5B
  • Power: N/A
  • Status: Planned
  • Sponsors: Beale Infrastructure, Unknown hyperscaler

CoreWeave/Core Scientific Muskogee Data Center

  • Location: Muskogee
  • Investment: $4.0B
  • Power: 100 MW
  • Status: Under Construction
  • Sponsors: CoreWeave, Core Scientific

Google Stillwater Data Center Campus

  • Location: Stillwater
  • Investment: $3.0B
  • Power: N/A
  • Status: Under Construction
  • Sponsors: Google LLC

Project Anthem (Tulsa East)

  • Location: Tulsa
  • Investment: $800M
  • Power: N/A
  • Status: Planned
  • Sponsors: Unknown (believed to be Meta Platforms)

Polaris Technologies Bitcoin Mining Data Center

  • Location: Muskogee
  • Investment: $100M
  • Power: 200 MW
  • Status: Under Construction
  • Sponsors: Polaris Technologies Inc.

TierPoint Oklahoma City Data Center Expansion

  • Location: Oklahoma City
  • Investment: $30M
  • Power: N/A
  • Status: Operational
  • Sponsors: TierPoint LLC

Cerebras Systems Oklahoma City AI Data Center

  • Location: Oklahoma City
  • Investment: N/A
  • Power: 10 MW
  • Status: Operational
  • Sponsors: Cerebras Systems, Scale Datacenters

DAMAC/EDGNEX Oklahoma Data Centers

  • Location: Unknown
  • Investment: N/A
  • Power: N/A
  • Status: Planned
  • Sponsors: DAMAC Group, EDGNEX Data Centers