Under Construction

Polaris Technologies Bitcoin Mining Data Center

Oklahoma — Muskogee , Muskogee County
Mega-Project
$100M
Investment
200 MW
Power Capacity
1
Sponsors

Sponsors & Partners

Project Timeline

Announced
2024-02
Construction Start
2024-02
Expected Completion
2025

Current canonical record

42-acre site. Phase 2 expansion could double capacity to 400 MW, making it one of the largest cryptocurrency mining sites in the world.

Located at Port Muskogee, John T. Griffin Industrial Park. Project Bifrost. Specializes in Bitcoin data center infrastructure. Expected to create 20 jobs. Construction began in early 2024. Company optimistic about Phase 2 expansion to double capacity.

Record provenance

This page is generated from the reviewed project database snapshot. The record was last reviewed on 2026-02-05. Blank fields mean the value was not publicly disclosed or could not be reconciled safely; they do not mean zero.