Approximately 70 MW of critical IT load for NVIDIA GPUs, 30 MW for ancillary systems. Part of 500 MW contract worth $8.7 billion over 12 years.
Core Scientific announced a plan to scale its Muskogee campus to about 1.5 GW of gross power, or about 1.0 GW of leasable power, including an agreement to acquire Polaris DS LLC and its 440 MW gross-power position with OG&E. Core Scientific also said construction had begun on a second unleased 82.5 MW building, with initial delivery expected in Q4 2027, while the current leased 70 MW building was in final testing and commissioning for Q2 2026 delivery to its customer.
Record provenance
This page is generated from the reviewed project database snapshot. The record was last reviewed on 2026-07-17. Blank fields mean the value was not publicly disclosed or could not be reconciled safely; they do not mean zero.