Arkansas
Arkansas hosts 9 documented datacenter projects representing $21.0B in announced investment and 1.6 GW of power capacity.
State Overview 9 documented projects
$21.0B
Announced Investment
1.6 GW
Planned Power Capacity
#30
Investment Rank
#36
Power Rank
Project Status Breakdown
Under Construction
3
33% of projects
Planned
3
33% of projects
Operational
2
22% of projects
Canceled
1
11% of projects
All Projects in Arkansas
9 projects| Project | Location | Investment | Power | Status |
|---|---|---|---|---|
| Clarksville Data Center Serverfarm, SF ARK1 LLC... | Clarksville | $8.0B | N/A | Under Construction |
| AVAIO Digital Leo AVAIO Digital Partners, Entergy Arkansas | Little Rock | $6.0B | 1.1 GW | Under Construction |
| Google West Memphis Data Center (Project Pyramid) Google LLC | West Memphis | $4.0B | N/A | Under Construction |
| Little Rock Port Data Center (Willowbend Capital) Willowbend Capital LLC, Google LLC | Little Rock | $1.0B | N/A | Planned |
| Conway Data Center (Forgelight Ventures) Forgelight Ventures LLC, Unknown Fortune 100 Company | Conway | $1.0B | N/A | Planned |
| Project Pulse - Gum Springs Data Center DC Devco LLC, unnamed end buyer | Gum Springs | $1.0B | N/A | Canceled |
| Ritter Communications Data Technology Center Ritter Communications | Jonesboro | $8M | 0.75 MW | Operational |
| Apollo Project - Helena Harbor Data Center Stadium Partners, Garrison Data Partners | Helena | N/A | 500 MW | Planned |
| TierPoint Little Rock Data Center TierPoint | Little Rock | N/A | N/A | Operational |
Arkansas hosts 9 documented datacenter projects representing $21.0B in disclosed investment and 1.6 GW of power capacity.
Key Statistics
| Metric | Value |
|---|---|
| Total Projects | 9 |
| Total Investment | $21.0B |
| Total Power Capacity | 1.6 GW |
| Investment Rank | #30 |
| Power Rank | #36 |
| Grid Operator | SPP/MISO |
Project Status Breakdown
- Planned: 3 projects
- Under Construction: 3 projects
- Operational: 2 projects
- Canceled: 1 project
Top Projects
Clarksville Data Center
- Location: Clarksville
- Investment: $8.0B
- Power: N/A
- Status: Under Construction
- Sponsors: Serverfarm, SF ARK1 LLC, Vaughn Property Group
AVAIO Digital Leo
- Location: Little Rock
- Investment: $6.0B
- Power: 1.1 GW
- Status: Under Construction
- Sponsors: AVAIO Digital Partners, Entergy Arkansas
Google West Memphis Data Center (Project Pyramid)
- Location: West Memphis
- Investment: $4.0B
- Power: N/A
- Status: Under Construction
- Sponsors: Google LLC
Conway Data Center (Forgelight Ventures)
- Location: Conway
- Investment: $1.0B
- Power: N/A
- Status: Planned
- Sponsors: Forgelight Ventures LLC, Unknown Fortune 100 Company
Little Rock Port Data Center (Willowbend Capital)
- Location: Little Rock
- Investment: $1.0B
- Power: N/A
- Status: Planned
- Sponsors: Willowbend Capital LLC, Google LLC
Project Pulse - Gum Springs Data Center
- Location: Gum Springs
- Investment: $1.0B
- Power: N/A
- Status: Canceled
- Sponsors: DC Devco LLC, unnamed end buyer
Ritter Communications Data Technology Center
- Location: Jonesboro
- Investment: $8M
- Power: 0.75 MW
- Status: Operational
- Sponsors: Ritter Communications
Apollo Project - Helena Harbor Data Center
- Location: Helena
- Investment: N/A
- Power: 500 MW
- Status: Planned
- Sponsors: Stadium Partners, Garrison Data Partners
TierPoint Little Rock Data Center
- Location: Little Rock
- Investment: N/A
- Power: N/A
- Status: Operational
- Sponsors: TierPoint