Overview
Oklahoma is building out both gas and solar capacity to meet rising demand, anchored by Google’s Pryor data center and the growing SPP grid. OG&E and PSO are adding nearly 1 GW of combined-cycle and combustion turbine capacity, while Leeward Renewable Energy has announced over 700 MW of solar projects under long-term PPAs with Google. SPP’s interconnection queue holds 71 Oklahoma projects totaling 23.8 GW, signaling both opportunity and bottleneck risk for new generation.
Generation Projects
Natural Gas
OG&E and PSO are driving most of the near-term natural gas buildout.
- OG&E Horseshoe Lake Units 11-12: Two GE 7FA.05 combustion turbines totaling 448 MW, approved in 2023 and planned for service in 2026.[1]
- OG&E Tinker Units 1-2: Two GE LM6000 combustion turbines at Tinker Air Force Base near Oklahoma City, 88 MW total, also slated for 2026.[1]
- PSO Green Country acquisition: PSO signed an agreement to purchase the 795 MW Green Country combined-cycle plant, with an application filed at the Oklahoma Corporation Commission in September 2024.[2]
- OG&E future additions: OG&E’s 2025 IRP identifies Horseshoe Lake Units 13-14 and a 5-year capacity purchase agreement with the Tenaska Kiamichi combined-cycle plant as selected resources pending regulatory filings.[1]
Solar
Google’s long-term PPAs are anchoring a large Oklahoma solar portfolio.
- Leeward/Google Mayes County Solar Portfolio: Construction is underway on 372 MW near Google’s Pryor data center, including Salt Branch (145 MW), Huckleberry (125 MW), and Mayes Solar (102 MW).[4]
- Twelvemile Solar Projects 1-3: Leeward’s Twelvemile Solar 1 and 2 add 152.5 MW, and Twelvemile 3 adds 200 MW, bringing the total Oklahoma solar portfolio to 724 MW under Google PPAs.[4]
Wind
PSO’s 2024 IRP includes wind additions later in the decade.
- PSO preferred plan: Adds 200 MW of new wind in 2032 and totals 753 MW of new wind resources across the full plan period.[2]
Transmission and Grid
SPP is planning new transmission lines and incorporating large load growth into its regional transmission plan.
- Mathewson-to-Redbud 345 kV line: SPP selected Transource Oklahoma to build this 38.4-mile line at an estimated cost of $72 million, with completion expected in 2027.[5]
- SPP ITP upgrades: SPP’s 2025-2026 Integrated Transmission Plan incorporates large load growth assumptions, including data center-scale additions, to get ahead of projected demand.[6]
Battery Storage
Both OG&E and PSO are planning utility-scale battery projects.
- PSO preferred plan: Includes 200 MW of 6-hour storage in 2029.[2]
- OG&E Black Kettle BESS: OG&E’s 2025 IRP identifies a 20-year capacity purchase agreement with the Black Kettle battery storage project, pending regulatory filings.[1]
Data Center Power Agreements
Google is the dominant data center customer in Oklahoma.
- Google PPAs for Oklahoma solar: Leeward Renewable Energy’s Oklahoma solar portfolio is supported by long-term PPAs with Google, with output from the Mayes County projects delivered via firm transmission service to the Grand River Dam Authority for use at Google’s Pryor data center.[4]
Interconnection Queue
SPP’s queue reforms have not eliminated the backlog.
- SPP GI backlog mitigation: SPP revised its generator interconnection procedures in January 2022 to address queue congestion, including changes to study timelines.[7]
- Oklahoma projects in SPP queue: As of January 8, 2026, the SPP Active queue lists 71 Oklahoma projects in DISIS stage, totaling 23.8 GW of nameplate capacity — a massive cluster that implies long study timelines and higher upgrade costs for new generation.[8]
- Large-load planning pressure: SPP’s ITP studies now explicitly incorporate large-load growth assumptions, a signal that transmission planning is catching up to demand from data centers and other high-load users.[6]
What to Watch
- PSO Green Country acquisition: The Oklahoma Corporation Commission decision on PSO’s purchase of the 795 MW combined-cycle plant will determine whether that capacity comes online as planned.
- SPP queue processing: With 23.8 GW of Oklahoma projects in the queue, any changes to SPP’s interconnection procedures or cost allocation could reshape timelines for new generation.
- Google’s next PPAs: Google has committed to over 700 MW of Oklahoma solar; watch for any additional PPAs or expansions at the Pryor data center.
Sources
[1] Oklahoma Gas & Electric, “2025 Integrated Resource Plan” (prepared 2025), Oklahoma Corporation Commission filing, https://oklahoma.gov/content/dam/ok/en/occ/documents/pu/pud-reports-page/2025-oge-irp.pdf (accessed January 8, 2026).
[2] Public Service Company of Oklahoma, “2024 Integrated Resource Plan (IRP) Report” (2024), https://www.psoklahoma.com/lib/docs/community/projects/PSO_2024_IRP_Report.pdf (accessed January 8, 2026).
[3] U.S. Nuclear Regulatory Commission, “Oklahoma | NRC Facility Locator” (page last reviewed March 9, 2021), https://www.nrc.gov/info-finder/region-state/oklahoma.html (accessed January 8, 2026).
[4] Kelsey Misbrener, “Leeward Renewable Energy announces over 700 MW of Oklahoma solar for Google,” Solar Power World, January 15, 2025, https://www.solarpowerworldonline.com/2025/01/leeward-renewable-energy-announces-over-700-mw-of-oklahoma-solar-for-google/ (accessed January 8, 2026).
[5] Southwest Power Pool, “SPP board selects Transource to construct $72 million Oklahoma transmission project,” May 7, 2025, https://www.spp.org/news-list/spp-board-selects-transource-to-construct-72-million-oklahoma-transmission-project/ (accessed January 8, 2026).
[6] Southwest Power Pool, “SPP Update for Oklahoma Corporation Commission (June 2025)” (presentation), Oklahoma Corporation Commission, June 2025, https://oklahoma.gov/content/dam/ok/en/occ/documents/ajls/jls-courts/court-clerk/meetings/meeting-presentations-2025/SPP%20Update%20for%20Oklahoma%20Corporation%20Commission%20June%202025.pdf (accessed January 8, 2026).
[7] Southwest Power Pool, “Generator Interconnection” (webpage), https://www.spp.org/engineering/generator-interconnection/ (accessed January 8, 2026).
[8] Southwest Power Pool, “SPP GI Active Queue” (public queue table), https://opsportal.spp.org/Studies/GIActive (accessed January 8, 2026).