Overview
Nevada is racing to connect its isolated northern and southern grids while building over a gigawatt of solar-plus-storage capacity. The Greenlink transmission system will nearly double Northern Nevada’s import capacity by 2027, but until then a single 525 kV line is the only north-south tie. Google has already locked in 115 MW of enhanced geothermal power from Fervo Energy, signaling that tech companies see Nevada as a viable data center power market once transmission constraints ease.
Generation Projects
Natural Gas
NV Energy’s 2024 IRP (integrated resource plan — a utility’s long-term blueprint for meeting demand) includes natural gas peaking plants to backstop intermittent renewables.
- North Valmy peaking units: ~400 MW of gas peakers co-located at the North Valmy Generating Station, targeting summer 2028 to serve Northern Nevada reliability needs.[1]
Solar
Nevada’s solar pipeline is dominated by large-scale projects paired with four-hour battery storage.
- Libra Solar: Up to 700 MW solar + 700 MW storage on BLM land in Mineral County; NEPA review completed in 2024 and project is in NV Energy’s procurement pipeline.[1][3]
- Dry Lake East: 200 MW solar + 200 MW battery (800 MWh) expected in service by end of 2026 in Clark County.[1]
- Boulder Solar III: 128 MW solar + 128 MW battery (511 MWh) targeting June 2027 in Boulder City’s El Dorado Valley.[1]
- Gemini Solar + Storage (operational): 690 MW solar paired with 380 MW battery (1,400 MWh) near Las Vegas; one of the largest co-located solar-plus-storage projects in the U.S., brought online in 2024.[4]
Geothermal
Google’s 2025 power supply agreement with NV Energy adds 115 MW of enhanced geothermal from Fervo Energy to the grid, delivering around-the-clock clean power to Google’s Nevada data centers and cloud region.[9]
Wind
Wind development has stalled. The BLM denied the right-of-way application for the 500 MW Crescent Peak Wind project near Searchlight in 2024, leaving Nevada with a thin near-term wind pipeline.[5]
Transmission and Grid
Nevada’s grid is split into northern and southern systems with only one existing link — a reliability constraint that Greenlink is designed to fix.
- Greenlink West: A 472-mile, 525 kV line between Las Vegas and Reno; the federal Record of Decision was issued September 9, 2024, and the project is moving toward construction.[6]
- Greenlink North: A ~235-mile, 525 kV line from Ely to Yerington with new substations; Draft EIS issued September 2024, with Final EIS and Record of Decision pushed into 2025.[7]
- Northern Nevada import limit: Currently capped at 1,275 MW and fully allocated; Greenlink West will raise the limit to 2,000 MW by Q1 2027, and Greenlink North will boost it further to 2,800 MW by Q1 2029.[11]
- Single north-south tie: The ON Line 525 kV is the only existing connection between NV Energy’s northern and southern systems, underscoring the urgency of Greenlink completion.[11]
Battery Storage
NV Energy’s 2024 IRP solar pipeline includes over 1,000 MW of battery storage co-located with over 1,000 MW of solar. Three major solar-plus-storage PPAs (power purchase agreements — long-term electricity contracts) anchor this buildout: Dry Lake East (200 MW/800 MWh), Boulder Solar III (128 MW/511 MWh), and Libra (700 MW/2,800 MWh).[1]
Data Center Power Agreements
- Google + NV Energy + Fervo: Google’s Nevada energy supply agreement adds 115 MW of enhanced geothermal power to the grid, delivered by NV Energy from Fervo Energy to support Google’s Nevada data centers and cloud region.[9]
Interconnection Queue
Nevada faces the same national queue backlog affecting the entire Western grid. Berkeley Lab’s 2024 “Queued Up” report found ~11,600 active projects representing 1,570 GW of generation and 1,030 GW of storage in interconnection queues nationwide, with the typical project taking nearly 5 years to reach operation in 2023.[10]
Northern Nevada’s 1,275 MW import limit is fully allocated, creating a hard ceiling on new generation until Greenlink West comes online in 2027.[11]
What to Watch
- Greenlink West construction timeline: Federal permits are in hand as of September 2024; monitor construction progress toward the Q1 2027 in-service date, which will unlock 725 MW of additional import capacity into Northern Nevada.
- Greenlink North Final EIS: The Draft EIS was issued in September 2024; watch for the Final EIS and Record of Decision in 2025, which will set the stage for the Ely-to-Yerington 525 kV link and another 800 MW of transfer capacity by 2029.
- Libra Solar permitting-to-construction transition: With NEPA review complete and the project in NV Energy’s 2024 IRP, track whether Libra’s 700 MW solar + 700 MW storage moves to construction on schedule.
Sources
[1] NV Energy. “NV Energy’s 2024 Integrated Resource Plan (IRP) Info Sheet.” 2024. https://www.nvenergy.com/publish/content/dam/nvenergy/brochures_arch/cleanenergy/IRP-Info-Sheet.pdf (accessed January 8, 2026).
[2] U.S. Energy Information Administration. “Nevada State Energy Profile and Energy Estimates.” Last updated June 20, 2025. https://www.eia.gov/state/analysis.php?sid=NV (accessed January 8, 2026).
[3] Bureau of Land Management. “Libra Solar Project.” NEPA Register project page (last updated September 16, 2024). https://eplanning.blm.gov/eplanning-ui/project/2022592/510 (accessed January 8, 2026).
[4] pv magazine USA. “690 MW solar-plus-storage project in U.S. now operational in Nevada.” July 19, 2024. https://pv-magazine-usa.com/2024/07/19/largest-solar-plus-storage-project-in-u-s-now-operational-in-nevada/ (accessed January 8, 2026).
[5] Bureau of Land Management. “Crescent Peak Wind Project.” NEPA Register project page (project status: ROW application denied). n.d. https://eplanning.blm.gov/eplanning-ui/project/81663/510 (accessed January 8, 2026).
[6] Bureau of Land Management. “Greenlink West Transmission Project.” NEPA Register project page, Record of Decision September 9, 2024 (last updated November 14, 2025). https://eplanning.blm.gov/eplanning-ui/project/2017391/510 (accessed January 8, 2026).
[7] Bureau of Land Management. “Greenlink North Transmission Project.” NEPA Register project page (last updated January 7, 2026). https://eplanning.blm.gov/eplanning-ui/project/2017033/510 (accessed January 8, 2026).
[8] NV Energy. “Greenlink Nevada Updates - September 2024.” September 2024. https://www.nvenergy.com/cleanenergy/greenlink-nevada/greenlink-sept-2024 (accessed January 8, 2026).
[9] Google. “Google’s new model for clean energy approved in Nevada.” May 13, 2025. https://blog.google/feed/nevada-clean-energy/ (accessed January 8, 2026).
[10] Lawrence Berkeley National Laboratory. “Queued Up: 2024 Edition, Characteristics of Power Plants Seeking Transmission Interconnection As of the End of 2023.” April 2024. https://emp.lbl.gov/sites/default/files/2024-04/Queued%20Up%202024%20Edition_R2.pdf (accessed January 8, 2026).
[11] NV Energy (OATI OASIS). “Greenlink Transmission Project: Approach for Posting Total and Available Transfer Capability on the OASIS to Allow Transmission and Interconnection Service Applications.” October 26, 2022. https://www.oasis.oati.com/woa/docs/NEVP/NEVPdocs/Greenlink_TTC_and_ATC_Summary.pdf (accessed January 8, 2026).