Overview
West Virginia passed a sweeping data center incentive package in 2025 centered on projects with 90 MW or greater critical IT load. The state offers fast-track certification, special property tax rules, and a microgrid program that lets qualifying projects build on-site generation with minimal Public Service Commission oversight. In exchange, the state preempts county and municipal zoning, permitting, and land-use regulation for certified projects.
Incentives
High Impact Data Center Certification
The Department of Economic Development certifies qualifying data centers within 14 days of notification.[1] Certification unlocks access to the microgrid program and special property tax treatment.
Certified Microgrid Development Program
Certified microgrid districts can serve data centers with on-site or district-level generation and distribution. Key features include:
- Reduced PSC oversight — microgrids are exempt from traditional rate regulation and certificates of convenience and necessity for generation and distribution within the district.[3]
- Special contract path — the PSC can approve special contracts between microgrid customers and utilities, or set terms within 90 days if parties fail to agree after a 120-day negotiation period.[3]
- Cost isolation — regulated utility customers outside the microgrid district cannot be charged for microgrid generation, transmission, or distribution costs. All costs must be borne by the microgrid generator or district customers.[3]
Special Property Tax Valuation
High impact data center property placed in service after July 1, 2025, is subject to a special valuation method and tax distribution framework. A portion of incremental property tax revenue flows to state and county funds, including the Personal Income Tax Reduction Fund and an Electric Grid Stabilization and Security Fund.[2] This framework sunsets on December 31, 2055.[4]
Requirements and Conditions
Minimum Thresholds
A high impact data center must have a critical IT load of 90 MW or more and be placed in service on or after July 1, 2025.[2]
Microgrid District Limits
Microgrid districts are capped at 2,250 acres, must be nearly contiguous, and can deliver no more than 10% of generated electricity outside the district (only to wholesale markets).[3] A district must attract at least two businesses, and the program is limited to two districts statewide unless more than 70% of microgrid power is consumed by high impact data centers.[3]
Prohibited Arrangements
The state bars payment-in-lieu-of-taxes (PILOT) agreements and tax increment financing (TIF) projects for both microgrid property and high impact data center property subject to the special valuation rules.[2][3]
Retained Local Obligations
Despite state preemption of zoning and permitting (see below), certified projects must still pay:
- Municipal business and occupation tax
- Local sales and use tax
- Ad valorem property taxes (under the special valuation framework)
- Municipal service fees
- Utility charges based on cost of service[5]
Projects must also comply with the State Building Code (Rule 87 CSR 4).[5]
Utility and Grid Rules
Special Contract Mechanism
The PSC can approve special contracts between certified microgrid districts and incumbent utilities. If parties fail to reach agreement after a 120-day negotiation period, the PSC must set contract terms within 90 days.[3]
Cost Allocation Firewall
State law prohibits charging regulated utility customers outside a microgrid district for costs associated with microgrid generation, transmission, or distribution. This firewall is designed to prevent cost-shifting to residential and commercial ratepayers elsewhere in West Virginia.[3]
Local Zoning
State Preemption of Local Control
West Virginia preempts all county and municipal regulation of certified microgrid districts and certified high impact data centers. Preempted areas include:
- Zoning
- Land-use regulation
- Noise and lighting ordinances
- Building permitting and inspections
- Local licensing requirements[5]
Counties and municipalities cannot require local consent for state or county actions tied to these projects, including approval of TIF districts.[5]
What to Watch
- PSC implementation — watch for special contract filings or microgrid certification petitions since the July 2025 effective date.
- Local government response — county commissions and planning bodies may seek legislative amendments to restore some local oversight or negotiating leverage.
- 2026 legislative session — potential amendments to the Power Generation and Consumption Act (HB 2014) or related data center tax provisions.
Sources
[1] West Virginia Code, “§5B-2-21a. Data Centers,” West Virginia Legislature, 2025, https://code.wvlegislature.gov/5B-2-21a/ (accessed January 8, 2026).
[2] West Virginia Code, “§11-6N-2. Definitions” and “§11-6N-4. Special Rules for Tax Distribution of High Impact Data Centers,” West Virginia Legislature, 2025, https://code.wvlegislature.gov/11-6N-2/ and https://code.wvlegislature.gov/11-6N-4/ (accessed January 8, 2026).
[3] West Virginia Code, “§5B-2-21. Certified Microgrid Development Program,” West Virginia Legislature, 2025, https://code.wvlegislature.gov/5B-2-21/ (accessed January 8, 2026).
[4] West Virginia Code, “§11-6N-5. Termination,” West Virginia Legislature, 2025, https://code.wvlegislature.gov/11-6N-5/ (accessed January 8, 2026).
[5] West Virginia Code, “§5B-2-21b. Authority to assist certified microgrid district projects and certified high impact data center projects; legislative findings,” West Virginia Legislature, 2025, https://code.wvlegislature.gov/5B-2-21b/ (accessed January 8, 2026).
[6] Jericho Casper, “New West Va. Law Grants Sweeping Exemptions to Attract Data Centers,” Broadband Breakfast, May 2, 2025, https://broadbandbreakfast.com/new-west-va-law-grants-sweeping-exemptions-to-attract-data-centers/ (accessed January 8, 2026).
[7] West Virginia Legislature, “Enrolled Committee Substitute for House Bill 2014 (Power Generation and Consumption Act),” passed April 12, 2025 (effective July 11, 2025), https://code.wvlegislature.gov/signed_bills/2025/2025-RS-HB2014-SUB%20ENR_signed.pdf (accessed January 8, 2026).