West Virginia

West Virginia hosts 13 documented datacenter projects representing $24.1B in announced investment and 18.7 GW of power capacity.

State Overview 13 documented projects
$24.1B
Announced Investment
18.7 GW
Planned Power Capacity
#30
Investment Rank
#6
Power Rank

Project Status Breakdown

Planned
8
62% of projects
Operational
3
23% of projects
Under Construction
2
15% of projects

All Projects in West Virginia

13 projects
Project Location Investment Power Status
Nscale / Microsoft Monarch Compute Campus AI Infrastructure Phase
Nscale, Microsoft...
Point Pleasant area $20.0B 8.0 GW Under Construction
Penzance Bedington Data Center Campus
Penzance Management
Falling Waters District $4.0B 600 MW Planned
NETL Computational Science and Engineering Center
National Energy Technology Laboratory, U.S. Department of Energy
Morgantown $46M 3.55 MW Under Construction
IRS Enterprise Computing Center
Internal Revenue Service, US Federal Government
Kearneysville $23M 1.8 MW Operational
Alpha Technologies Huntington Data Center
Alpha Technologies Inc.
Huntington $20M N/A Planned
Alpha Technologies Data Center DC1
Alpha Technologies Inc
South Charleston $14M 2 MW Operational
Dedispec Data Center
Dedispec
Berkeley Springs $7M 1 MW Operational
Fundamental Data Tucker County Data Center
Fundamental Data LLC
Between Thomas and Davis N/A 5.2 GW Planned
Adams Fork Data Center Energy Campus - Harless Site
TransGas Development Systems LLC
Holden N/A 2.4 GW Planned
Adams Fork Data Center Energy Campus - Wharncliffe Site
TransGas Development Systems LLC
Wharncliffe N/A 2.5 GW Planned
Berkeley/Jefferson County Data Center Campus
IB10 Martinsburg LLC
Near Kearneysville N/A N/A Planned
Google Putnam County Data Center Campus
Google
Buffalo N/A N/A Planned
Ryan Stuart Summit Point Data Center Project
Ryan Stuart Development
Summit Point N/A N/A Planned

West Virginia hosts 13 documented datacenter projects representing $24.1B in disclosed investment and 18.7 GW of power capacity.

Key Statistics

MetricValue
Total Projects13
Total Investment$24.1B
Total Power Capacity18.7 GW
Investment Rank#30
Power Rank#6
Grid OperatorPJM

Project Status Breakdown

  • Planned: 8 projects
  • Operational: 3 projects
  • Under Construction: 2 projects

Top Projects

Nscale / Microsoft Monarch Compute Campus AI Infrastructure Phase

  • Location: Point Pleasant area
  • Investment: $20.0B
  • Power: 8.0 GW
  • Status: Under Construction
  • Sponsors: Nscale, Microsoft, NVIDIA, Caterpillar, Fidelis New Energy, American Intelligence & Power Corporation

Penzance Bedington Data Center Campus

  • Location: Falling Waters District
  • Investment: $4.0B
  • Power: 600 MW
  • Status: Planned
  • Sponsors: Penzance Management

NETL Computational Science and Engineering Center

  • Location: Morgantown
  • Investment: $46M
  • Power: 3.55 MW
  • Status: Under Construction
  • Sponsors: National Energy Technology Laboratory, U.S. Department of Energy

IRS Enterprise Computing Center

  • Location: Kearneysville
  • Investment: $23M
  • Power: 1.8 MW
  • Status: Operational
  • Sponsors: Internal Revenue Service, US Federal Government

Alpha Technologies Huntington Data Center

  • Location: Huntington
  • Investment: $20M
  • Power: N/A
  • Status: Planned
  • Sponsors: Alpha Technologies Inc.

Alpha Technologies Data Center DC1

  • Location: South Charleston
  • Investment: $14M
  • Power: 2 MW
  • Status: Operational
  • Sponsors: Alpha Technologies Inc

Dedispec Data Center

  • Location: Berkeley Springs
  • Investment: $7M
  • Power: 1 MW
  • Status: Operational
  • Sponsors: Dedispec

Fundamental Data Tucker County Data Center

  • Location: Between Thomas and Davis
  • Investment: N/A
  • Power: 5.2 GW
  • Status: Planned
  • Sponsors: Fundamental Data LLC

Adams Fork Data Center Energy Campus - Wharncliffe Site

  • Location: Wharncliffe
  • Investment: N/A
  • Power: 2.5 GW
  • Status: Planned
  • Sponsors: TransGas Development Systems LLC

Adams Fork Data Center Energy Campus - Harless Site

  • Location: Holden
  • Investment: N/A
  • Power: 2.4 GW
  • Status: Planned
  • Sponsors: TransGas Development Systems LLC