Kansas hosts 9 documented datacenter projects representing $128.8B in announced investment and 1.8 GW of power capacity.

State Overview 9 documented projects
$128.8B
Announced Investment
1.8 GW
Planned Power Capacity
#2
Investment Rank
#18
Power Rank

Project Status Breakdown

Planned
4
44% of projects
Operational
3
33% of projects
Under Construction
1
11% of projects
Expansion
1
11% of projects

All Projects in Kansas

9 projects
Project Location Investment Power Status
Project Kestrel
Hunt Midwest
Kansas City $100.0B N/A Planned
Red Wolf DCD Properties Data Center Campus
Red Wolf DCD Properties LLC
Kansas City $12.6B 600 MW Planned
Project Mica (Google AI Campus)
Google LLC, AG Rose Solutions LLC...
Kansas City $10.0B 700 MW Planned
De Soto Data Center Campus (Project Pilot)
Mount Sunflower Properties, LLC, Beale Infrastructure...
De Soto $3.1B N/A Planned
Meta Kansas City Data Center (Golden Plains Technology Park)
Meta Platforms, Inc.
Kansas City $1.0B N/A Operational
Google Kansas City Data Center (Hunt Midwest Business Center)
Google LLC, Alphabet Inc.
Kansas City $1.0B 400 MW Under Construction
Patmos AI Campus (Kansas City Star Building)
Patmos
Kansas City $1.0B 100 MW Expansion
Edged Data Centers Kansas City
Edged Energy, Evergy
Kansas City $143M 26 MW Operational
Iron Mountain Kansas City Underground Data Center (KCM-1)
Iron Mountain
Kansas City N/A 3.9 MW Operational

Kansas Data Center Infrastructure

Kansas hosts 9 documented datacenter projects representing $128.8B in disclosed investment and 1.8 GW of power capacity.

Key Statistics

MetricValue
Total Projects9
Total Investment$128.8B
Total Power Capacity1.8 GW
Investment Rank#2
Power Rank#18
Grid OperatorSPP

Project Status Breakdown

  • Planned: 4 projects
  • Operational: 3 projects
  • Under Construction: 1 projects
  • Expansion: 1 projects

Top Projects

Project Kestrel

  • Location: Kansas City
  • Investment: $100.0B
  • Power: N/A
  • Status: Planned
  • Sponsors: Hunt Midwest

Red Wolf DCD Properties Data Center Campus

  • Location: Kansas City
  • Investment: $12.6B
  • Power: 600 MW
  • Status: Planned
  • Sponsors: Red Wolf DCD Properties LLC

Project Mica (Google AI Campus)

  • Location: Kansas City
  • Investment: $10.0B
  • Power: 700 MW
  • Status: Planned
  • Sponsors: Google LLC, AG Rose Solutions LLC, Diode Ventures LLC

De Soto Data Center Campus (Project Pilot)

  • Location: De Soto
  • Investment: $3.1B
  • Power: N/A
  • Status: Planned
  • Sponsors: Mount Sunflower Properties, LLC, Beale Infrastructure, Blue Owl

Meta Kansas City Data Center (Golden Plains Technology Park)

  • Location: Kansas City
  • Investment: $1.0B
  • Power: N/A
  • Status: Operational
  • Sponsors: Meta Platforms, Inc.

Google Kansas City Data Center (Hunt Midwest Business Center)

  • Location: Kansas City
  • Investment: $1.0B
  • Power: 400 MW
  • Status: Under Construction
  • Sponsors: Google LLC, Alphabet Inc.

Patmos AI Campus (Kansas City Star Building)

  • Location: Kansas City
  • Investment: $1.0B
  • Power: 100 MW
  • Status: Expansion
  • Sponsors: Patmos

Edged Data Centers Kansas City

  • Location: Kansas City
  • Investment: $143M
  • Power: 26 MW
  • Status: Operational
  • Sponsors: Edged Energy, Evergy

Iron Mountain Kansas City Underground Data Center (KCM-1)

  • Location: Kansas City
  • Investment: N/A
  • Power: 3.9 MW
  • Status: Operational