Mega-Project
$860M
Investment
151.5 MW
Power Capacity
400,000 sq ft
Total Area
1
Sponsors
Sponsors & Partners
DAMAC Digital
Project Timeline
Announced
2026-05-12
Expected Completion
2027
Current canonical record
This record tracks Heartland Data Center Project in Kansas.
After the Planning Commission denied DAMAC Digital's final site plan application in June, DAMAC filed an appeal for a July 16, 2026 City Council hearing and separately submitted a revised final site plan application scheduled for Planning Commission consideration on August 11, 2026. The proposal remains appeal/revision-pending rather than finally canceled.
Record provenance
This page is generated from the reviewed project database snapshot. The record was last reviewed on 2026-07-19. Blank fields mean the value was not publicly disclosed or could not be reconciled safely; they do not mean zero.