Planned

White Cloud Acres AI Data Center

Missouri — Maryville area , Nodaway County
Mega-Project
$6.3B
Investment
600 MW
Power Capacity
3
Sponsors

Sponsors & Partners

Project Timeline

Announced
2026-06-03

Current canonical record

This record tracks White Cloud Acres AI Data Center in Missouri.

New project: Scale Microgrids, described as formerly ReLoad Energy, presented White Cloud Acres as a $6.3 billion AI data center and co-located natural-gas power plant along US Highway 71 about eight miles south of Maryville. The proposal includes a 600 MW generation facility dedicated to the data center, has no announced hyperscale tenant, and was described as targeting AI applications.

Record provenance

This page is generated from the reviewed project database snapshot. The record was last reviewed on 2026-07-17. Blank fields mean the value was not publicly disclosed or could not be reconciled safely; they do not mean zero.