Planned

TeraWulf Lake Hawkeye (Cayuga)

New York — Lansing , Tompkins County
Mega-Project
138 MW
Power Capacity
1
Sponsors

Sponsors & Partners

Project Timeline

Announced
2019
Construction Start
2020
Expected Completion
2032-02

Current canonical record

Former coal plant under an 80-year lease; permitting-stage plan with 138 MW phase-one power access and 320 MW ultimate critical IT capacity

Part of Empire State Data Hub initiative; originally owned by Riesling Power LLC; could power 500k homes at max capacity; environmental concerns from local groups; QA 2026-07-19: Corrected status to permitting/planned and cleared modeled investment.

Record provenance

This page is generated from the reviewed project database snapshot. The record was last reviewed on 2026-07-19. Blank fields mean the value was not publicly disclosed or could not be reconciled safely; they do not mean zero.