Project Timeline
Current canonical record
Includes 600MW substation; project seeking expansion beyond initial scope
Revised GCEDC SEQR application dated February 18, 2026 describes Project Double Reed as a 2.2 million-square-foot campus with three two-story buildings on 90 permanent development acres plus 40 temporary construction-logistics acres, approximately 500 MW of utility power, 12 emergency diesel generators, and 120+ to 125 permanent jobs. Data Center Dynamics reported on March 9, 2026 that GCEDC said the revised application increased capital investment to $19.46 billion, up from earlier $6.3 billion and $11.81 billion figures. Sponsors identified as Stream Data Centers and Apollo Global Management.
Record provenance
This page is generated from the reviewed project database snapshot. The record was last reviewed on 2026-06-15. Blank fields mean the value was not publicly disclosed or could not be reconciled safely; they do not mean zero.