Mega-Project
$1.6B
Investment
400 MW
Power Capacity
1
Sponsors
Sponsors & Partners
Ryan Companies
Project Timeline
Announced
2025-01-10
Current canonical record
This record tracks Southwest Crossing Data Center in Arizona.
Data Center Dynamics reported on 2025-01-16 that Pinal County's Planning and Zoning Commission recommended approval for Ryan Companies' Southwest Crossing data-center campus on about 172 acres between Phoenix and Tucson, describing a four-building, 1.4 million-square-foot campus with roughly 400 MW of expected demand and an estimated $1.6 billion development cost.
Record provenance
This page is generated from the reviewed project database snapshot. The record was last reviewed on 2026-07-18. Blank fields mean the value was not publicly disclosed or could not be reconciled safely; they do not mean zero.