Mega-Project
$1.7B
Investment
240 MW
Power Capacity
2
Sponsors
Sponsors & Partners
QTS Realty Trust
Blackstone
Project Timeline
Announced
2024
Construction Start
2028-01
Expected Completion
2027-06-11
Current canonical record
200 acres acquired for expansion
QTS filed with the US Army Corps of Engineers to develop RIC 5 south of its existing White Oak Technology Park campus, one of three planned buildings at the site.
Record provenance
This page is generated from the reviewed project database snapshot. The record was last reviewed on 2026-06-15. Blank fields mean the value was not publicly disclosed or could not be reconciled safely; they do not mean zero.