Sponsors & Partners
Project Timeline
Current canonical record
Up to 16 buildings with 6.6M sq ft data center space and 400K sq ft office space. First building 350-440K sq ft
ATL2 East should be treated as an expansion of the existing QTS Fayetteville/Project Excalibur campus, not a separate near-duplicate. DCA DRI #4603 was completed after February 1, 2026 and reports QTS Eastwood, LLC as developer, a 313-acre site west of Veterans Parkway, $3B estimated value at build-out, about $29M estimated annual local tax revenues, about 100 FTEs, 0.20 MGD water demand, and on-site substation/new transmission infrastructure. The accessible DCA Part 2 form leaves peak MW as TBD. Existing campus context: 615-acre Project Excalibur/QTS Fayetteville campus around 20 miles south of Atlanta.
Record provenance
This page is generated from the reviewed project database snapshot. The record was last reviewed on 2026-06-15. Blank fields mean the value was not publicly disclosed or could not be reconciled safely; they do not mean zero.