Planned

QTS - Blakely

Georgia — Blakely , Early
Mega-Project
1
Sponsors

Sponsors & Partners

Project Timeline

Announced
2026-03-10

Current canonical record

This record tracks QTS - Blakely in Georgia.

DCA DRI #4651 lists QTS Technology Services as developer for a data center-type project at coordinates 31.406296, -84.912908. The initial form reports 12,000,000 square feet and a Q4 2035 completion target; the DRI remained at initial-form-submitted status in the DCA table as of the June 15, 2026 sweep.

Record provenance

This page is generated from the reviewed project database snapshot. The record was last reviewed on 2026-06-15. Blank fields mean the value was not publicly disclosed or could not be reconciled safely; they do not mean zero.