Project Timeline
Announced
2026-01-09
Current canonical record
This record tracks Project Delta Stokes County Data Center in North Carolina.
Project Delta proposed multiple data center buildings on roughly 1,800 acres near US 311 and Tuttle Road along the Dan River. In April 2026 Stokes County voided the January rezoning and text amendment after notice defects were raised in litigation, so any future application must restart the local process. Public reporting describes the campus as several hundred megawatts, but no exact MW was disclosed.
Record provenance
This page is generated from the reviewed project database snapshot. The record was last reviewed on 2026-06-15. Blank fields mean the value was not publicly disclosed or could not be reconciled safely; they do not mean zero.