Mega-Project
$1.0B
Investment
400 MW
Power Capacity
2
Sponsors
Sponsors & Partners
Camreon Grogan
Project Turbo LLC
Project Timeline
Announced
2026-01-10
Current canonical record
This record tracks Project Azelea in Georgia.
DCA DRI #4602 was completed after February 1, 2026. The initial form describes six data center buildings on 200 acres at 2660-2358 Randall Hunt Road, with special-exception action and 2029 completion. The Part 2 form reports $1B estimated value at build-out, $25M estimated annual local tax revenue, 125 FTEs, Jefferson Energy service, and 400 MW peak connected load.
Record provenance
This page is generated from the reviewed project database snapshot. The record was last reviewed on 2026-06-15. Blank fields mean the value was not publicly disclosed or could not be reconciled safely; they do not mean zero.