Under Construction

PowerHouse Reno Data Center

Nevada — Reno/Sparks , Storey County
Mega-Project
200 MW
Power Capacity
2
Sponsors

Sponsors & Partners

Project Timeline

Announced
2024-01
Construction Start
2024
Expected Completion
2025-late

Current canonical record

49 acres at Tahoe Reno Industrial Center; three-building, 900,000-square-foot campus. Current operator page lists 200 MW; the earlier announcement described 65 MW of bridging power.

PowerHouse's first site outside of northern Virginia. Joint venture between PowerHouse and Harrison Street. Expected online late 2025. Will serve increasing data demands of leading hyperscale users.; Investment estimated at $7M/MW; QA 2026-07-18: Updated campus power from the earlier 65 MW bridging figure to the operator's current 200 MW specification.

Record provenance

This page is generated from the reviewed project database snapshot. The record was last reviewed on 2026-07-18. Blank fields mean the value was not publicly disclosed or could not be reconciled safely; they do not mean zero.