Sponsors & Partners
Project Timeline
Current canonical record
400,000 square foot, five-acre campus. Currently 35 MW total capacity (10 MW newly added). Target 100 MW when fully built out.
Located at 1601 McGee Street, downtown Kansas City, Missouri. Former Kansas City Star printing press building converted to data center. Billion-dollar retrofit project. Supports high-density GPU, HPC, and AI infrastructure. Rack-ready colocation space in increments of 2.5 MW, supporting densities of 100 kW or more per rack. Campus extends beyond traditional data center functions with office space, conference facilities, and entertainment areas. Patmos assumed operations in November 2024. Nebius is the first client, marking their entry into North American market. [State corrected KS->MO 2026-06-10: site is in Missouri (Platte/Clay/Jackson County) per primary sources.]
Record provenance
This page is generated from the reviewed project database snapshot. The record was last reviewed on 2026-06-15. Blank fields mean the value was not publicly disclosed or could not be reconciled safely; they do not mean zero.