Operational

NTT Global Data Centers Sacramento Campus

California — Sacramento , Sacramento County
Mega-Project
$369M
Investment
52.7 MW
Power Capacity
1
Sponsors

Sponsors & Partners

Project Timeline

Construction Start
2014-06
Expected Completion
2014-11

Current canonical record

Three data centers: CA1 (12.6MW), CA2 (26.1MW), CA3 (14MW)

Combined campus with 52.7MW capacity. Seismically stable location, lowest cost power for wholesale data centers in California.; Investment estimated at $7M/MW

Record provenance

This page is generated from the reviewed project database snapshot. The record was last reviewed on 2026-06-15. Blank fields mean the value was not publicly disclosed or could not be reconciled safely; they do not mean zero.