Operational

Novva Tahoe Reno Data Center

Nevada — Reno/Sparks , Storey County
Mega-Project
60 MW
Power Capacity
1
Sponsors

Sponsors & Partners

Project Timeline

Announced
2023-05
Construction Start
2023
Expected Completion
2024

Current canonical record

20-acre campus with six 10MW data halls at Tahoe-Reno Industrial Center

Launched in July 2025. Features 54-inch raised flooring and dedicated on-site 100MW N+1 substation. Direct-to-chip compatible cooling. Fourth completed Novva location alongside Colorado Springs, West Jordan (Utah), and North Las Vegas.; Investment estimated at $7M/MW