Updated July 2026: the Essential Edition and its companion database are refreshedGet it on Amazon
Operational

Novva Tahoe Reno Data Center

Nevada — Reno/Sparks, Storey County
Mega-Project
$500M
Investment
60 MW
Power Capacity
300,000 sq ft
Total Area
1
Sponsors

Sponsors & Partners

Project Timeline

Announced
2023-05
Construction Start
2023
Expected Completion
2024

Current canonical record

20-acre campus with six 10MW data halls at Tahoe-Reno Industrial Center

Launched in July 2025. Features 54-inch raised flooring and dedicated on-site 100MW N+1 substation. Direct-to-chip compatible cooling. Fourth completed Novva location alongside Colorado Springs, West Jordan (Utah), and North Las Vegas.; Investment estimated at $7M/MW

Record provenance

This page is generated from the reviewed project database snapshot. The record was last reviewed on 2026-06-15. Blank fields mean the value was not publicly disclosed or could not be reconciled safely; they do not mean zero.