Expansion

NJFX Project Cool Water

New Jersey — Wall Township , Monmouth
Mega-Project
10 MW
Power Capacity
1
Sponsors

Sponsors & Partners

Project Timeline

Announced
2025-12-04

Current canonical record

This record tracks NJFX Project Cool Water in New Jersey.

New untracked expansion at NJFX's Wall cable landing station campus. Data Center Dynamics reported that NJFX announced a new 10 MW high-density, liquid-to-chip AI data hall, internally named Project Cool Water, supported by an executed utility load letter and $3 million deposit, with power delivery targeted by the end of 2026. The existing NJFX facility totals 64,800 square feet and hosts multiple subsea cable systems.

Record provenance

This page is generated from the reviewed project database snapshot. The record was last reviewed on 2026-06-15. Blank fields mean the value was not publicly disclosed or could not be reconciled safely; they do not mean zero.