This record tracks Microsoft Silver Springs Data Center in Nevada.

Lyon County Planning Commission minutes from February 10, 2026 say Microsoft requested conditional use permits for substations at 1200 W US Highway 50 in Silver Springs to support a data center campus under separate review, that staff was working on an ADR application for a Microsoft data center, and that the substations would tie into the Greenlink project. The minutes also note anticipated substation construction in 2028-2029 and recommendation votes for the Nighthawk and 120-kV substation items.

Record provenance

This page is generated from the reviewed project database snapshot. The record was last reviewed on 2026-07-17. Blank fields mean the value was not publicly disclosed or could not be reconciled safely; they do not mean zero.