This record tracks Microsoft - Project Rita (Tyrone) in Georgia.
The Town of Tyrone identifies the approved local project as the Microsoft data center project approved by Town Council in March 2024. As of June 2, 2026, zoning approval remained in place, but Microsoft had not submitted a site plan, land disturbance permit, building permit, or other development permits, so construction could not begin. The same page says Microsoft did not request abatements or other incentives from the town and estimates operational water consumption at about 4,000 gallons per day.