Planned

Microsoft - Project Rita (Tyrone)

Georgia — Tyrone , Fayette
Mega-Project
$350M
Investment
1
Sponsors

Sponsors & Partners

Project Timeline

Announced
2026-05-05

Current canonical record

This record tracks Microsoft - Project Rita (Tyrone) in Georgia.

The Town of Tyrone identifies the approved local project as the Microsoft data center project approved by Town Council in March 2024. As of June 2, 2026, zoning approval remained in place, but Microsoft had not submitted a site plan, land disturbance permit, building permit, or other development permits, so construction could not begin. The same page says Microsoft did not request abatements or other incentives from the town and estimates operational water consumption at about 4,000 gallons per day.

Record provenance

This page is generated from the reviewed project database snapshot. The record was last reviewed on 2026-06-15. Blank fields mean the value was not publicly disclosed or could not be reconciled safely; they do not mean zero.