Under Construction

Microsoft Manassas Jacksonville Road Campus

Virginia — Manassas , Prince William County
Mega-Project
$672M
Investment
96 MW
Power Capacity
1
Sponsors

Sponsors & Partners

Project Timeline

Construction Start
2024-01
Expected Completion
2025-12-31

Current canonical record

This record tracks Microsoft Manassas Jacksonville Road Campus in Virginia.

Site preparation work began January 2024 by Lemartec, rock removal started September 2024; From Microsoft Local: 96 MW NOVEC substation confirmed; investment estimated at M/MW

Record provenance

This page is generated from the reviewed project database snapshot. The record was last reviewed on 2026-06-15. Blank fields mean the value was not publicly disclosed or could not be reconciled safely; they do not mean zero.