Under Construction

Microsoft - East Point Campus

Georgia — East Point , Fulton
Mega-Project
$1.8B
Investment
324 MW
Power Capacity
1
Sponsors

Sponsors & Partners

Project Timeline

Announced
2021-02-11
Construction Start
2023
Expected Completion
2026

Current canonical record

125-acre site on Ben Hill Road. Reduced from three to two datacenter buildings based on community feedback

Part of Microsoft's East US 3 Azure region. First phase includes one data center building, power substation, privacy screening, and support facilities.; Power estimated at 100 W/sqft from 700,000 sqft; 125-acre campus ATL06/ATL07; investment at M/MW

Record provenance

This page is generated from the reviewed project database snapshot. The record was last reviewed on 2026-06-15. Blank fields mean the value was not publicly disclosed or could not be reconciled safely; they do not mean zero.