Operational

Meta Kansas City Data Center (Golden Plains Technology Park)

Missouri — Kansas City , Clay/Platte
Mega-Project
$1.0B
Investment
750 MW
Power Capacity
2
Sponsors

Sponsors & Partners

Project Timeline

Announced
2022-03
Construction Start
2022

Current canonical record

Expanded from original $800M investment. Part of larger Golden Plains Technology Park with capacity for up to 12 data centers totaling 4.31M sq ft

Opened August 2025 with over 100 jobs. Located at Golden Plains Technology Park at I-435 and US-169. Generated 1,500 construction jobs at peak.

Record provenance

This page is generated from the reviewed project database snapshot. The record was last reviewed on 2026-06-15. Blank fields mean the value was not publicly disclosed or could not be reconciled safely; they do not mean zero.