Mega-Project
$1.5B
Investment
214 MW
Power Capacity
1
Sponsors
Sponsors & Partners
Meta Platforms, Inc.
Project Timeline
Announced
2018
Construction Start
2018
Expected Completion
2022-12
Current canonical record
Expanded from initial 970,000 sq ft to nearly 3.5 million sq ft with multiple expansion phases.
Located at 5400 Prosperity Dr NW. Supports over 300 operational jobs. Combined with Montgomery, Meta's total Alabama investment exceeds $3 billion.; .5B expansion announced June 2022; construction paused Dec 2022; 214 MW estimated from investment
Record provenance
This page is generated from the reviewed project database snapshot. The record was last reviewed on 2026-06-15. Blank fields mean the value was not publicly disclosed or could not be reconciled safely; they do not mean zero.