This record tracks Energy Storage Solutions Kingsboro Data Center in North Carolina.
Energy Storage Solutions withdrew its proposed Edgecombe County AI data center in July 2026 while county officials were discussing a 24-month data center moratorium. The project was planned for the Kingsboro development area near Tarboro; the source describes an initial eight-phase 300 MW proposal on a 52-acre parcel, notes reports varied up to a possible 900 MW final campus, and states the developer had appealed an earlier denial.
Record provenance
This page is generated from the reviewed project database snapshot. The record was last reviewed on 2026-07-17. Blank fields mean the value was not publicly disclosed or could not be reconciled safely; they do not mean zero.