Operational

Edged Data Centers Kansas City

Missouri — Kansas City , Jackson County
Mega-Project
$143M
Investment
26 MW
Power Capacity
2
Sponsors

Sponsors & Partners

Project Timeline

Announced
2024-06
Construction Start
2024
Expected Completion
2024-12

Current canonical record

26 MW critical capacity (expanded from original 18 MW plan)

Located at 3420 North Arlington Avenue near downtown Kansas City, Missouri. Opened December 11, 2024. Designed to support advanced computing technology, cloud services, and high-density artificial intelligence workloads. Partnership between Edged Energy and Evergy (local utility provider). [State corrected KS->MO 2026-06-10: site is in Missouri (Platte/Clay/Jackson County) per primary sources.]

Record provenance

This page is generated from the reviewed project database snapshot. The record was last reviewed on 2026-06-15. Blank fields mean the value was not publicly disclosed or could not be reconciled safely; they do not mean zero.