Under Construction

EdgeCore Silicon Valley Campus

California — Santa Clara , Santa Clara County
Mega-Project
$440M
Investment
72 MW
Power Capacity
2
Sponsors

Sponsors & Partners

Project Timeline

Announced
2022
Construction Start
2023-01
Expected Completion
2025

Current canonical record

Two purpose-built data centers on 12 acres

Located at 2201 Laurelwood Road, Santa Clara. $440 million financing secured in 2024 to accelerate development.; Investment estimated at $7M/MW

Record provenance

This page is generated from the reviewed project database snapshot. The record was last reviewed on 2026-06-15. Blank fields mean the value was not publicly disclosed or could not be reconciled safely; they do not mean zero.