Mega-Project
196 MW
Power Capacity
1
Sponsors
Sponsors & Partners
EdgeCore Digital Infrastructure
Project Timeline
Announced
2024-07-18
Construction Start
2026-04-22
Expected Completion
2029-06
Current canonical record
120 acres acquired for development
1.4 million square foot campus with 120 acres; Investment estimated at $7M/MW
Record provenance
This page is generated from the reviewed project database snapshot. The record was last reviewed on 2026-06-15. Blank fields mean the value was not publicly disclosed or could not be reconciled safely; they do not mean zero.