This record tracks EdgeConneX New Albany Data Center Campus in Ohio.
Data Center Dynamics reported that EdgeConneX affiliate PowerConneX proposed a third on-site natural gas plant to power a planned New Albany data center campus. The 430 MW figure is proposed on-site generation capacity, not confirmed IT load. EdgeConneX's PowerConneX II project page describes a natural-gas-fired generation facility on about 48.9 acres with up to 216 MW intended to serve a data center on the same site.
Record provenance
This page is generated from the reviewed project database snapshot. The record was last reviewed on 2026-06-15. Blank fields mean the value was not publicly disclosed or could not be reconciled safely; they do not mean zero.