Under Construction

Digi Power X Columbiana AI Data Center

Alabama — Columbiana , Shelby County
Mega-Project
$372M
Investment
40 MW
Power Capacity
2
Sponsors

Sponsors & Partners

Project Timeline

Announced
2026-05-05

Current canonical record

This record tracks Digi Power X Columbiana AI Data Center in Alabama.

Digi Power X announced a master services agreement with Cerebras for a purpose-built 40 MW AI data center campus in Columbiana. The initial 10-year contract is valued at about $1.1 billion, with up to $2.5 billion including renewals. Phase 1 is 15 MW, Phase 2 adds 25 MW, construction was to commence immediately, Phase 1 ready-for-service is targeted for December 15, 2026, and full deployment is targeted by the end of Q1 2027.