Mega-Project
$154M
Investment
60 MW
Power Capacity
1
Sponsors
Sponsors & Partners
PowerHouse Data Centers
Project Timeline
Announced
2023-05-12
Construction Start
2024-04
Expected Completion
2025
Current canonical record
This record tracks CyrusOne ABX-1 Ashburn (PowerHouse Lease) in Virginia.
30-year powered shell lease deal, construction began April 2024; From DCD: 60 MW PowerHouse lease (expandable to 80 MW), 265,000 sqft; acquired for 54.1M; 30-year lease to CyrusOne
Record provenance
This page is generated from the reviewed project database snapshot. The record was last reviewed on 2026-06-15. Blank fields mean the value was not publicly disclosed or could not be reconciled safely; they do not mean zero.