This record tracks Crusoe Warrenton Campus in Missouri.
New project: Warrenton's cost-benefit analysis identifies Warrenton DC Owner 1 LLC as a Crusoe affiliate and describes a data center on about 336 acres at 22151 NW Service Road. The plan assumes Phase 1 in 2027 with an approximately 800,000-square-foot data center building and 40,000-square-foot administration building, and Phase 2 in 2028 with a second approximately 800,000-square-foot data center building. The investment figure sums stated initial Phase 1 and Phase 2 equipment costs plus real-property improvement assumptions, while noting the bond documents do not obligate completion of both phases.