Mega-Project
$6.0B
Investment
1.0 GW
Power Capacity
1
Sponsors
Sponsors & Partners
CRG
Project Timeline
Announced
2026-03-20
Current canonical record
This record tracks CRG Festus Data Center in Missouri.
Festus mayoral materials said a development-agreement framework had been reached with CRG for a data center project, with about 150 jobs, no real-property tax abatement, and developer responsibility for required infrastructure upgrades. The financial model identifies an initial 300 MW power load in 2028 and full 1 GW load in 2031.
Record provenance
This page is generated from the reviewed project database snapshot. The record was last reviewed on 2026-06-15. Blank fields mean the value was not publicly disclosed or could not be reconciled safely; they do not mean zero.