Operational

CoreSite NY3

New Jersey — Secaucus , Hudson County
Mega-Project
$105M
Investment
15 MW
Power Capacity
1
Sponsors

Sponsors & Partners

Project Timeline

Announced
2023
Expected Completion
2024-Q4

Current canonical record

Four-story building with three data halls (5MW each) totaling over 90,000 sq ft of raised floor space. Adjacent to NY2 facility.

Completed in September 2025. Adds 138,000+ sq ft to CoreSite's NY metro footprint. Purpose-built with AI-ready infrastructure including liquid cooling. Forms highly connected campus with NY2.; Investment estimated at $7M/MW

Record provenance

This page is generated from the reviewed project database snapshot. The record was last reviewed on 2026-06-15. Blank fields mean the value was not publicly disclosed or could not be reconciled safely; they do not mean zero.