Mega-Project
$105M
Investment
15 MW
Power Capacity
1
Sponsors
Sponsors & Partners
CoreSite
Project Timeline
Announced
2023
Expected Completion
2024-Q4
Current canonical record
Four-story building with three data halls (5MW each) totaling over 90,000 sq ft of raised floor space. Adjacent to NY2 facility.
Completed in September 2025. Adds 138,000+ sq ft to CoreSite's NY metro footprint. Purpose-built with AI-ready infrastructure including liquid cooling. Forms highly connected campus with NY2.; Investment estimated at $7M/MW