Mega-Project
250 MW
Power Capacity
1
Sponsors
Sponsors & Partners
The Agency Broome County IDA/LDC
Project Timeline
Announced
2025-10-30
Current canonical record
This record tracks Broome County Tech Park Data Center in New York.
NYISO's load-project queue lists The Agency's Broome County Tech Park as a 250 MW load project with DAT end use in Broome County, submitted October 30, 2025, with a 345 kV point of interconnection via a loop on the Oakdale-Fraser Line 32 and proposed initial backfeed in December 2029. Public queue aggregators identify the project as an active/proposed data-center load; no investment figure or end user was found.
Record provenance
This page is generated from the reviewed project database snapshot. The record was last reviewed on 2026-07-17. Blank fields mean the value was not publicly disclosed or could not be reconciled safely; they do not mean zero.