Planned

Amazon Web Services - Douglas County Campus

Georgia — Douglasville , Douglas
Mega-Project
$5.0B
Investment
786 MW
Power Capacity
1
Sponsors

Sponsors & Partners

Project Timeline

Announced
2025-01

Current canonical record

Part of $11B total investment across Butts and Douglas counties. Multiple land acquisitions totaling ~400 acres

Expected to create at least 275 high-skilled jobs. AWS purchased 118 acres in October 2024 for $37M, 156 acres in September for $37.1M, and 129 acres in November for $64.7M. 15-year property tax break approved.; Power estimated at $7M/MW

Record provenance

This page is generated from the reviewed project database snapshot. The record was last reviewed on 2026-06-15. Blank fields mean the value was not publicly disclosed or could not be reconciled safely; they do not mean zero.