Mega-Project
$5.0B
Investment
714 MW
Power Capacity
2
Sponsors
Sponsors & Partners
Unknown site evaluator under NDA
Town of Wiscasset
Project Timeline
Announced
2025-09-18
Current canonical record
$5 billion AI hyperscale facility proposal
Shelterforce, republishing The Daily Yonder, reported on June 18, 2026 that the prospective $5 billion Wiscasset data center had not broken ground and that the 300-acre Old Ferry Road site remained undeveloped as of publication. The article also reported that on March 3, 2026 Lincoln County reallocated Wiscasset's federal housing funds to Waldoboro and Newcastle after the town's handling of the data center prospect shifted the original housing-funded plan.
Record provenance
This page is generated from the reviewed project database snapshot. The record was last reviewed on 2026-07-17. Blank fields mean the value was not publicly disclosed or could not be reconciled safely; they do not mean zero.