Planned

Wildcat Ridge AI Data Center Campus

Pennsylvania — Archbald , Lackawanna County
Mega-Project
$2.1B
Investment
1.6 GW
Power Capacity
2
Sponsors

Sponsors & Partners

Current canonical record

This record tracks Wildcat Ridge AI Data Center Campus in Pennsylvania.

Wildcat Ridge is a proposed Archbald data center campus on a roughly one-square-mile or 400-plus-acre wooded tract, with plans reported for 14 three-story data center buildings. DeSmog reported the zoning application indicated a 1.6 GW power need; other local reporting describes a $2.1 billion investment estimate and continuing 2026 public hearings.

Record provenance

This page is generated from the reviewed project database snapshot. The record was last reviewed on 2026-06-15. Blank fields mean the value was not publicly disclosed or could not be reconciled safely; they do not mean zero.