Mega-Project
1.8 GW
Power Capacity
1
Sponsors
Sponsors & Partners
Tract
Project Timeline
Announced
2024-01
Expected Completion
2028
Current canonical record
668+ acres master-planned data center park
Cleanview's July 2026 Utah tracker identifies two named Tract Eagle Mountain developments under the tracked Project Tripletail land position: Pole Canyon, a planned 844-acre data center with 1,700 MW capacity, and Pony Express, a planned 225-acre data center with 120 MW capacity. Combined named-site capacity is 1,820 MW. Sources do not disclose investment.
Record provenance
This page is generated from the reviewed project database snapshot. The record was last reviewed on 2026-07-17. Blank fields mean the value was not publicly disclosed or could not be reconciled safely; they do not mean zero.