This record tracks Tract - Norwalk Project West Data Center Campus in Iowa.
Norwalk City Council approved a development agreement with Tract on March 5, 2026 for a 282-acre site west of Highway 28 and south of Delaware Street, previously described as Project West and a future data center project. DCD reported city expectations of about $12B total investment, no tax incentives requested, about 600 construction jobs, and 80 high-quality permanent jobs. The city emphasized that the vote does not itself approve a data center and that any future data center would need separate city-level, state, federal, and public-review steps.
Record provenance
This page is generated from the reviewed project database snapshot. The record was last reviewed on 2026-07-18. Blank fields mean the value was not publicly disclosed or could not be reconciled safely; they do not mean zero.