Related Digital
CoreWeave
Clayco
Project Timeline
Announced
2025-10-07
Construction Start
2025-10-07
Expected Completion
2026-12
Current canonical record
115-acre campus. Phase 1 is 184,000 sq ft providing 88 MW to CoreWeave. Total campus capacity: 302 MW.
June 2026 reporting from a site tour said work was nearing completion on the first 184,000-square-foot phase of Related Digital's Cheyenne campus and that the first phase was expected to be finished in late 2026. The update confirms continued construction progress and late-2026 first-phase target for the $1.2 billion, 302 MW campus with CoreWeave as anchor tenant.
Record provenance
This page is generated from the reviewed project database snapshot. The record was last reviewed on 2026-07-17. Blank fields mean the value was not publicly disclosed or could not be reconciled safely; they do not mean zero.