Three-story 138,000-square-foot building with 12 MW current utility power expandable to 16.5 MW and 3 MW of critical IT load
Located at 1500 Champa Street in heart of Denver's interconnection alley. N+1 redundancy in power and cooling systems. Ability to interconnect to 20+ networks and long-haul fiber providers. RadiusDC launched in 2022 as new North America Metro Edge data center platform.; QA 2026-07-18: Normalized Denver County and corrected facility power to 12 MW while retaining 3 MW as critical IT load.
Record provenance
This page is generated from the reviewed project database snapshot. The record was last reviewed on 2026-07-18. Blank fields mean the value was not publicly disclosed or could not be reconciled safely; they do not mean zero.