Mega-Project
$200M
Investment
100 MW
Power Capacity
1
Sponsors
Sponsors & Partners
Teton Digital
Project Timeline
Announced
2025-02-18
Current canonical record
This record tracks Project Trinity in North Dakota.
Teton Digital sought to build a 100 MW liquid-cooled data center about eight miles south of Tioga. Williams County Commissioners authorized the company to begin work toward a conditional use permit. Reported plan included two phases: 30 MW using existing power by Q3/Q4 2025 and completion of a 100 MW colocation facility by the end of 2026 after a new substation with MWEC.
Record provenance
This page is generated from the reviewed project database snapshot. The record was last reviewed on 2026-06-15. Blank fields mean the value was not publicly disclosed or could not be reconciled safely; they do not mean zero.