Mega-Project Central Pennsylvania
$15.0B
Investment
1.4 GW
Power Capacity
2
Sponsors
Sponsors & Partners
Pennsylvania Data Center Partners
PowerHouse Data Centers
Project Timeline
Announced
2025-07-15
Construction Start
2025-11-28
Expected Completion
2032-06-07
Current canonical record
1.35 GW capacity with expandability up to 1.8 GW. Three data center campuses, each featuring six buildings and dedicated 450 MW substation.
Announced at Pennsylvania Energy and Innovation Summit before President Donald Trump. Located in Northeast's emerging AI corridor. Expected to generate over $65 million in direct tax revenue.
Record provenance
This page is generated from the reviewed project database snapshot. The record was last reviewed on 2026-06-15. Blank fields mean the value was not publicly disclosed or could not be reconciled safely; they do not mean zero.